Operating experience of an R.O. plant as pretreatment of the demineralizer system in a cogeneration plant

โœ Scribed by Ken Hamby; James Chen


Publisher
Elsevier Science
Year
1989
Tongue
English
Weight
483 KB
Volume
76
Category
Article
ISSN
0011-9164

No coin nor oath required. For personal study only.

โœฆ Synopsis


This paper discusses the cost-effectiveness of utilizing the B.C. process as a pretreatment to a demineraliser installed in a cogeneration plant. The regeneration cycle time of a demineraliser was extended from approximately 9 hours to almost 336 hours resulting in a substantial savings of the chemicals used for regeneration and minimum regenerant for deep well disposal. The pay back of the capital investment in the R.O. system was calculated to be less than two years.