On minimizing resource consumption with constraints on the makespan and the total completion time
โ Scribed by Stanislav H. Vasilev; Bob L. Foote
- Publisher
- Elsevier Science
- Year
- 1997
- Tongue
- English
- Weight
- 524 KB
- Volume
- 96
- Category
- Article
- ISSN
- 0377-2217
No coin nor oath required. For personal study only.
โฆ Synopsis
We investigate a single machine scheduling problem where the resource consumed depends on the release times of jobs. The objective is to minimize the total consumption subject to a constraint on the makespan or the total completion time.
Results by Li are extended to the case where the consumption function is convex decreasing. A further extension to multiple consumption functions is shown. Conditions for feasibility are developed in each case.