Conditions of Contract for EPC Turnkey Projects, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction:
FIDIC Conditions for EPC Turnkey Projects: Silver
✍ Scribed by Federation Internationale des Ingenieurs Conseils
- Publisher
- Thomas Telford Ltd
- Year
- 1999
- Tongue
- English
- Leaves
- 125
- Category
- Library
No coin nor oath required. For personal study only.
✦ Synopsis
Conditions of Contract for EPC Turnkey Projects, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction: providing a fully-equipped facility, ready for operation (at the "turn of the key"). This type of contract is usually negotiated between the parties.
✦ Table of Contents
1.1.2 Parties and Persons......Page 18
1.1.3 Dates, Tests, Periods and Completion......Page 19
1.1.5 Works and Goods......Page 20
(d) “written” or “in writing” means hand-written, type-written, printed or electronically made, and resulting in a permanent record.......Page 21
1.7 Assignment......Page 22
(c) in the case of Contractor’s Documents which are in the form of computer programs and other software, permit their use on any computer on the Site and other places as envisaged by the Contract, including replacements of any computers supplied by the Contractor.......Page 23
2.1 Right of Access to the Site......Page 24
(b) take actions similar to those which the Contractor is required to take under sub-paragraphs (a), (b) and (c) of Sub-Clause 4.8 [Safety Procedures] and under Sub-Clause 4.18 [Protection of the Environment].......Page 25
3.1 The Employer’s Representative......Page 26
3.5 Determinations......Page 27
(b) failure by the Contractor to pay the Employer an amount due, as either agreed by the Contractor or determined under Sub-Clause 2.5 [Employer’s Claims] or Clause 20 [Claims, Disputes and Arbitration], within 42 days after this agreement or determination,......Page 28
(c) the intended commencement of the Subcontractor’s work on the Site.......Page 29
(e) provide any Temporary Works (including roadways, footways, guards and fences) which may be necessary, because of the execution of the Works, for the use and protection of the public and of owners and occupiers of adjacent land.......Page 30
(a) the convenience of the public, or......Page 31
4.18 Protection of the Environment......Page 32
4.21 Progress Reports......Page 33
4.23 Contractor’s Operations on Site......Page 34
5.2 Contractor’s Documents......Page 35
5.4 Technical Standards and Regulations......Page 36
5.8 Design Error......Page 37
6.7 Health and Safety......Page 38
6.11 Disorderly Conduct......Page 39
7.4 Testing......Page 40
(c) execute any work which is urgently required for the safety of the Works, whether because of an accident, unforeseeable event or otherwise.......Page 41
(b) completing all work which is stated in the Contract as being required for the Works or Section to be considered to be completed for the purposes of taking over under Sub-Clause 10.1 [Taking Over of the Works and Sections].......Page 42
8.5 Delays Caused by Authorities......Page 43
8.8 Suspension of Work......Page 44
9.1 Contractor’s Obligations......Page 45
9.3 Retesting......Page 46
(b) reject the application, giving reasons and specifying the work required to be done by the Contractor to enable the Taking-Over Certificate to be issued. The Contractor shall then complete this work before issuing a further notice under this Sub-Clause.......Page 47
(d) failure by the Contractor to comply with any other obligation.......Page 48
11.5 Removal of Defective Work......Page 49
11.11 Clearance of Site......Page 50
(a) sub-paragraph (b) of Sub-Clause 11.1 [Completion of Outstanding Work and Remedying of Defects] shall apply, and......Page 51
13.1 Right to Vary......Page 52
13.4 Payment in Applicable Currencies......Page 53
13.7 Adjustments for Changes in Legislation......Page 54
(d) the amortisation rate for repayments, then it shall be calculated by dividing the total amount of the advance payment by the Contract Price stated in the Contract Agreement less Provisional Sums.......Page 55
14.4 Schedule of Payments......Page 56
14.7 Timing of Payments......Page 57
14.10 Statement at Completion......Page 58
14.14 Cessation of Employer’s Liability......Page 59
15.1 Notice to Correct......Page 60
(ii) for showing or forbearing to show favour or disfavour to any person in relation to the Contract,......Page 61
16.1 Contractor’s Entitlement to Suspend Work......Page 62
(c) remove all other Goods from the Site, except as necessary for safety, and leave the Site.......Page 63
17.2 Contractor’s Care of the Works......Page 64
17.5 Intellectual and Industrial Property Rights......Page 65
18.1 General Requirements for Insurance......Page 66
(b) copies of the policies for the insurances described in Sub-Clause 18.2 [Insurance of Works and Contractor’s Equipment] and Sub-Clause 18.3 [Insurance against Injury to Persons and Damage to Property].......Page 67
(iii) a part of the Works which has been taken over by the Employer, except to the extent that the Contractor is liable for the loss or damage, and......Page 68
18.4 Insurance for Contractor’s Personnel......Page 69
19.3 Duty to Minimise Delay......Page 70
(e) the Cost of repatriation of the Contractor’s staff and labour employed wholly in connection with the Works at the date of termination.......Page 71
(b) the Contractor shall send further interim claims at monthly intervals, giving the accumulated delay and/or amount claimed, and such further particulars as the Employer may reasonably require; and......Page 72
20.2 Appointment of the Dispute Adjudication Board......Page 73
20.4 Obtaining Dispute Adjudication Board’s Decision......Page 74
(c) the arbitration shall be conducted in the language for communications defined in Sub-Clause 1.4 [Law and Language].......Page 75
(b) the dispute may be referred directly to arbitration under Sub-Clause 20.6 [Arbitration].......Page 76
(ii) one of the three persons who are jointly called the “DAB” (or “dispute adjudication board”) and, where this is the case, the other two persons are called the “Other Members”.......Page 77
(ii) each day or part of a day up to maximum of two days travel time in each direction for the journey (if any) between the Member’s home and site or an other location of a meeting with Other Members (if any) and/or the Employer and the Contractor;......Page 79
📜 SIMILAR VOLUMES
his Second Edition of the Conditions of Contract for EPC/Turnkey Projects has been published by the Fédération Internationale des Ingénieurs-Conseils (FIDIC) as an update of the FIDIC 1999 Conditions of Contract for EPC/Turnkey Projects (Silver Book), First Edition. Along with the FIDIC 1999 Red
This Second Edition of the Conditions of Contract for Construction has been published by the Fédération Internationale des Ingénieurs-Conseils (FIDIC) as an update of the FIDIC 1999 Conditions of Contract for Construction (Red Book), First edition. Along with the FIDIC 1999 Yellow Book (the Cond
This Second Edition of the Conditions of Contract for Plant and Design-Build has been published by the Fédération Internationale des Ingénieurs-Conseils (FIDIC) as an update of the FIDIC 1999 Conditions of Contract for Plant and Design-Build (Yellow Book), First edition.
<p><span>Enables readers to easily understand the contract to enable better compliance and efficiency</span></p><p><span>Guide to the FIDIC Conditions of Contract for Construction: The Red Book 2017 </span><span>helps the reader overcome some of the difficulties encountered on a typical internationa